How Soon Can You Start Building Your New Home? Here’s What to Expect

If you’re thinking about building a new home, one of your first questions is probably: “How soon can we start building?” The good news is that, in many cases, you could be ready to break ground within as little as 2 to 3 months after beginning the planning process—if everything goes smoothly.

Of course, the full journey from your first consultation to moving in typically takes around 9 to 12 months, depending on your design, council approvals, builder availability, and weather. Here’s what that process looks like, with a focus on how quickly you can get started.

 

  1. Planning and Design (Start Building in as Little as 2–3 Months)

The planning phase is where your new home starts to take shape—and it’s also where you can gain momentum if you’re organized and decisive.

Designing Your Home (Typically 3–6 Months)

If you’re working with a building company or architect, creating and finalizing your plans can take anywhere from 3 to 6 months, depending on:

Fast-track tip: If you’re using pre-designed or modified plans, this process can be significantly quicker—allowing you to apply for consent and get started sooner.

Getting Building Consent (1–3 Months)

Once your plans are ready, they must be submitted to the local council for building consent. This process can take 1 to 3 months, depending on the council’s workload and whether additional documentation is required.

In the best-case scenario, if your design is straightforward and there are no delays:

 

  1. Construction (6–8 Months)

Once building consent is granted, construction can begin. Here’s a breakdown of the timeline:

Foundation (4–8 Weeks)

This includes site preparation, pouring the concrete slab or laying other types of foundations. It typically takes about a month or two, depending on site conditions and design complexity.

Framing to Fit-Out (22–26 Weeks)

Your home will start to take shape as the frame goes up, followed by the roof, windows, exterior cladding, plumbing, electrical, insulation, and interior finishes.

 

  1. Final Steps Before Move-In

Code Compliance Certificate (CCC)

Once the build is complete, the council will inspect the property and issue a CCC to confirm it meets building standards. This process can take anywhere from a few days to a couple of weeks.

Handover

With the CCC in hand, your builder will complete any final checks and hand over the keys. You’re now ready to move in!

 

Things That Can Speed Up or Delay the Start of Building

 

In Summary:

 

Ready to start building? The sooner you begin the planning phase, the sooner you can break ground. With the right preparation, your new home could be well underway before you know it.